Tower Southwest Natural Gas Comprehensive Utilization Project Successfully Put Into Operation
2023-01-06
On December 30, 2022, the core process equipment of the national key project tower southwest natural gas comprehensive utilization project was successfully put into operation and qualified products were produced. On January 2, 2023, with the successful start-up and operation of the thermal oil-water heat exchanger unit, all the equipment supplied by Whitett in this project has been successfully put into operation.
In the comprehensive utilization of natural gas in the southwest of the tower, our company undertakes the membrane separation and booster unit area (feed gas filter separator skid, feed gas heat exchanger skid, feed gas heater skid,2 sets of 900KW permeate compressors), dehydration unit area (360000 m3/day dehydration and mercury removal unit), air and nitrogen station (3 sets of compression and purification air skids, pressure swing adsorption nitrogen making skid), chilled water station (4 sets of natural cooling air-cooled chillers, 4 sets of chilled water circulating pumps) and heat exchange station (heat transfer oil-water heat exchange unit) and other major equipment, material supply, on-site reinstallation, commissioning and operation, etc.
The southwest tower project has a tight schedule and heavy tasks. the company has set up a project team led by the executive director. it has taken fine control measures in the process of design, procurement, material collection, production and manufacturing, quality inspection, transportation, on-site installation, etc. even in the face of many difficulties such as high-temperature power rationing, epidemic control and transportation difficulties in Xinjiang, all the equipment and materials supplied by our company are divided43 batches were shipped to the site in time, which fully guaranteed the project to be put into production and construction.
From August to October 2022, overcome many difficulties to ensure production.High temperature power-limiting self-generation, the outbreak control closed-loop production.
On October 23, 2022, the first group of field service personnel took a charter flight to the project site.
On October 31, 2022, the first batch of main units was successfully shipped.
On November 1, 2022, spanning nearly 8000 miles, the first main body device arrived smoothly..
December 5, 2022, the last set of installation completed.
December 28, 2022, nitrogen replacement.
On December 31, 2022, the core process unit was successfully put into operation..
Although the project has been put into production, in the next step, our company will continue to do a good job in on-site equipment training and production and operation, and make every effort to ensure the smooth operation of the device.